Windcross Bridge, Scour Repairs

Case Study Overview

Essential scour repairs using concrete bagwork to minor road bridge including mortar repairs and repointing to below water areas.

Diving contractor responsible for all health & safety planning and repair work including preparation of Diving Project Plan and Method Statements for forms of repair. Full liaison with client to obtain site access over private land adjacent to structure.

Low water levels precluded use of diving equipment so team reverted to placing bagwork via wading methods, wearing dry suits only. All concrete materials mixed on site and placed into starch lined hessian bags. Bagwork place by hand and secured using steel pins beneath abutment scour areas. Further bags placed and secure in channel as additional scour protection.

At a glance

  • Location: Windcross Bridge, Dymock, Gloucestershire
  • Date: March 2012
  • Project Value: Award Value £11, 244 final outturn £11,758 plus VAT. Increase due to cost of additional materials to carry out further work on site under Site Instruction to deal with extra scour areas reported by R7M
  • Programme Duration: 5 days on site including mob/demob, all work included extras completed in 4 days.
  • In-House resources Work: All works by R7M personnel – 5 man team
  • Contract: Gloucestershire Highways Subcontract Order

The Solution

All scheduled repair work delivered on time and within agreed budget.

Use of starch lined hessian bags to minimise washout of cement in to water course during placing of protective concrete bagwork. Low cost repair solution mitigating use of additional plant ie concrete mixer and pump on highway, road closures etc. Equivalent 5.5t of concrete carefully placed beneath vulnerable areas of bridge structure without use of formwork.

Value Added
Use of local sand/aggregate suppliers for concrete mix for bagwork. Material delivered to site in manageable quantities to ensure no wastage. Additional work carried out within original time budget – extra materials cost only. Minimal pollution of water course. Re survey area at start of job using R7M engineers to confirm extent of defect.

Before WorkWindcross Bridge

After Work
Windcross Bridge

THE MARINE PARTNER OF CHOICE

SEE RELATED CASE STUDIES

Brighton

Brighton Marina
Phase 2

In order to accommodate a new luxury apartment block in Brighton, part of the marina needed to be reclaimed using sheet piled cofferdams. This would enable the water to be kept out and foundations to be built for the stunning seafront properties. Red7Marine supported the installation of a sheet pile twin wall cofferdam.

Read more →

Oldbury

Oldbury

Red7Marine installed replacement Active Effluent Discharge Lines at Oldbury power station as part of the on-going care and maintenance works. Red7Marine’s previous project experience on similar projects consisting of works on subsea pipeline and outfalls at Bradwell and Sizewell nuclear power stations, positioned the company as the ideal marine partner for client, Magnox.

Read more →

Emirates

Emirates Cable Car

The Emirates cable car was installed to provide a pedestrian link across the River Thames between the Royal Docks and the Greenwich peninsula. Red7Marine worked with Bachy Soletanche in a joint venture to install the foundations for the one-kilometre long cable car using marine rotary bored piling.

Read more →

Battersea

Battersea River Pier

Red7Marine secured a contract at Battersea in December 2016 to install new tubular driven steel mooring piles for the Battersea Power Station river bus pontoon installation which is planned to be operational in Autumn 2017. Transport for London (TFL) decided to extend the river bus service after the number of housing developments at Battersea began to increase.

Read more →

Middleton

Middleton Sands Navigation Marker

This fast turn-around marine construction project involved the installation of a new tubular steel navigation marker pile at Middleton Sands, Barrow-in-Furness in 2017. The navigation marker was required to identify the sub surface obstructions and enable other vessels in the area to operate safely.

Read more →

Liverpool 2

Liverpool 2 Deep Water Port Extension

Red7Marine was the marine partner of choice for BAM Nuttall when they constructed a piled combi-wall as part of the Liverpool 2 Dock Expansion that began in 2014. The construction of the container terminal was supported by four of Red7Marine’s jack up barges; the Haven Seariser 1, Haven Seariser 2 and the Haven Seariser 3 and the Haven Seajack as it carried out rock socket piling works.

Read more →

Weston Super Mare

Weston-Super-Mare

The Red7Marine team was chosen to provide specialist marine plant and personnel to aid the redevelopment of the Weston-super-Mare Grand Pier after it was destroyed in a fire in 2008. Red7Marine supplied the Haven Seajack 4 assisted in the pier construction works. Its previous experience in pier and marina construction works made it the ideal project partner for this development.

Read more →

Bradwell

Bradwell Power Station Barrier Wall Removal

Red7Marine is a leading provider of equipment for marine demolition and is skilled in dismantling structures that are beyond the reach of ordinary demolition contractors. In 2012, Red7Marine removed approximately 800 tonnes of steel in the Blackwater Estuary from the Bradwell nuclear power station water intake structure.

Read more →

Fingringhoe

Fingringhoe Firing Ranges

Red7Marine installed scour protection and provided remediation on damaged sections of the flood defences to preserve areas of the salt marsh at the Fingringhoe firing ranges in Essex. Scour protection and remediation techniques are used to control erosion in both estuarine and the offshore environments.

Read more →

Get in touch with our expert team

or speak to our team: 01255 886710

British Standards ISO British Standards ISO British Standards ISO Achilles Building Confidence IEMA Construction Line Chas Ijuboa CPA National Workboat Association ICE Mates in Mind AF Covenenant Gold award

“Falmouth Divers Ltd contracted Red7Marine at the end of 2019 to undertake the installation of two rock-socketed piles at the Jupiter Point Royal Naval training facility near Torpoint. Red7Marine mobilised its SeaSeven jack-up vessel from Liverpool and transited it to Plymouth in early January through a gap in the seasonally bad weather. The mobilisation was conducted efficiently within a week as planned.”

Garry Duff, Engineer Falmouth Divers