Thames Gateway – Port Jetty

Case Study Overview

Red7Marine provided the marine plant & specialist personnel to undertake the construction of the new oil jetty installed in advance of the main reclamation works for the London Gateway Port development.

At a glance

  • Date: January 2009
  • Programme Duration: 22 months
  • Project Number: 2036
  • Value: £3.86m
  • Client: Laing O’Rourke
  • Principal Contractor: Laing O’Rourke

The Solution

The works comprised driven steel raking & vertical steel piles to support mooring & berthing dolphins together with driven steel clutched tubular piles to form an underwater retaining wall to the rear of the new berth pocket.

Red7Marine designed & fabricated the temporary works piling gates & deployed crane barges, transport pontoons & jack up barges, together with the associated crew & supervision, in order to facilitate construction.

Following piling works the berthing & mooring dolphins were constructed from pre-cats & cast in-situ reinforced concrete & in turn these were then fitted with fender units & mooring equipment.

Gunfleet Sands Windfarm
Get in touch with our expert team

or speak to our team: 01255 886710

British Standards ISO British Standards ISO British Standards ISO Achilles Building Confidence IEMA Construction Line Chas Ijuboa CPA National Workboat Association ICE Mates in Mind AF Covenenant Gold award

“Falmouth Divers Ltd contracted Red7Marine at the end of 2019 to undertake the installation of two rock-socketed piles at the Jupiter Point Royal Naval training facility near Torpoint. Red7Marine mobilised its SeaSeven jack-up vessel from Liverpool and transited it to Plymouth in early January through a gap in the seasonally bad weather. The mobilisation was conducted efficiently within a week as planned.”

Garry Duff, Engineer Falmouth Divers