Sladdens Pier Lowestoft

Case Study Overview

Sladdens Pier in Lowestoft is over 100 years old and provides protection for the Trawl Dock at the Port of Lowestoft. To protect both the structure and the Trawl Dock, Red7Marine carried out the construction of a new river wall in front of the offshore face of Sladdens Pier, providing ABP with security and greater longevity for their structure.

Red7Marine developed the scheme with its chosen designer, Robert Leeds Structural Design, since late last year, with work on site commencing early August 2022.

At a glance

  • Location: ABP Sladdens Pier, Lowestoft
  • Plant used: 250T Haven Seariser jack-up barge and Haven SeaStabler
  • What we did: Red7Marine was contracted to complete a £2M design and build project for Associated British Ports for the construction of a new river wall in front of Sladdens Pier in Lowestoft
sladdens pier

CHALLENGE

Red7Marine’s 250t deck capacity Haven Seariser 3 jack-up barge carried out a proof dig in September 2022 at the design locations of the pile wall. The barge was equipped with a 35t excavator from W M Plant Hire. The team carried out two dive surveys and extensive digging, several timber piles were removed as well as concrete and metal. All design sheet pile locations were also probed to highlight that the sheet piles could be installed safely and without risk of obstruction.

Following the final proof dig and dive survey, Red7Marine began piling activities.

sladdens pier

SOLUTION

Piling activities comprised of a continuous sheet piled wall formed using approx. no.100 sheet pile pairs spanning a length of 140m.

To carry out the piling activities, Red7Marine utilised its Haven SeaStabler as a flat top barge and the Haven Seariser 3 jack-up barge.

Both barges and a piling gate were secured and fixed into position in each pile location. Piles were lifted from the flat top material barge into the piling gate on the jack-up barge, and then were vibrated into the riverbed using a variable frequency piling hammer, this allows for a slow start method, which is a requirement for ecological preservation.

Pile installation progressed from north to south and required several barge moves in total on the northern side of Sladdens Pier. The barge was also positioned on the inside of the Trawl Dock for the final section of pile wall to reduce impact on the main navigational channel into Lowestoft. When all sheet piles were installed to design level, capping beams were installed across the top of the driven sheet pile wall.

The project was delivered successfully on time and within budget. Rob Page, Project Manager at ABP comments: “Really pleased with the overall product and how Red7 worked with ABP to deliver this project. Would have no hesitation in using them again.

sladdens pier

sladdens pier

THE MARINE PARTNER OF CHOICE

SEE RELATED CASE STUDIES

Brighton

Brighton Marina
Phase 2

In order to accommodate a new luxury apartment block in Brighton, part of the marina needed to be reclaimed using sheet piled cofferdams. This would enable the water to be kept out and foundations to be built for the stunning seafront properties. Red7Marine supported the installation of a sheet pile twin wall cofferdam.

Read more →

Oldbury

Oldbury

Red7Marine installed replacement Active Effluent Discharge Lines at Oldbury power station as part of the on-going care and maintenance works. Red7Marine’s previous project experience on similar projects consisting of works on subsea pipeline and outfalls at Bradwell and Sizewell nuclear power stations, positioned the company as the ideal marine partner for client, Magnox.

Read more →

Emirates

Emirates Cable Car

The Emirates cable car was installed to provide a pedestrian link across the River Thames between the Royal Docks and the Greenwich peninsula. Red7Marine worked with Bachy Soletanche in a joint venture to install the foundations for the one-kilometre long cable car using marine rotary bored piling.

Read more →

Battersea

Battersea River Pier

Red7Marine secured a contract at Battersea in December 2016 to install new tubular driven steel mooring piles for the Battersea Power Station river bus pontoon installation which is planned to be operational in Autumn 2017. Transport for London (TFL) decided to extend the river bus service after the number of housing developments at Battersea began to increase.

Read more →

Middleton

Middleton Sands Navigation Marker

This fast turn-around marine construction project involved the installation of a new tubular steel navigation marker pile at Middleton Sands, Barrow-in-Furness in 2017. The navigation marker was required to identify the sub surface obstructions and enable other vessels in the area to operate safely.

Read more →

Liverpool 2

Liverpool 2 Deep Water Port Extension

Red7Marine was the marine partner of choice for BAM Nuttall when they constructed a piled combi-wall as part of the Liverpool 2 Dock Expansion that began in 2014. The construction of the container terminal was supported by four of Red7Marine’s jack up barges; the Haven Seariser 1, Haven Seariser 2 and the Haven Seariser 3 and the Haven Seajack as it carried out rock socket piling works.

Read more →

Weston Super Mare

Weston-Super-Mare

The Red7Marine team was chosen to provide specialist marine plant and personnel to aid the redevelopment of the Weston-super-Mare Grand Pier after it was destroyed in a fire in 2008. Red7Marine supplied the Haven Seajack 4 assisted in the pier construction works. Its previous experience in pier and marina construction works made it the ideal project partner for this development.

Read more →

Bradwell

Bradwell Power Station Barrier Wall Removal

Red7Marine is a leading provider of equipment for marine demolition and is skilled in dismantling structures that are beyond the reach of ordinary demolition contractors. In 2012, Red7Marine removed approximately 800 tonnes of steel in the Blackwater Estuary from the Bradwell nuclear power station water intake structure.

Read more →

Fingringhoe

Fingringhoe Firing Ranges

Red7Marine installed scour protection and provided remediation on damaged sections of the flood defences to preserve areas of the salt marsh at the Fingringhoe firing ranges in Essex. Scour protection and remediation techniques are used to control erosion in both estuarine and the offshore environments.

Read more →

Get in touch with our expert team

or speak to our team: 01255 886710

British Standards ISO British Standards ISO British Standards ISO Achilles Building Confidence IEMA Construction Line Chas Ijuboa CPA National Workboat Association ICE Mates in Mind AF Covenenant Gold award

“I wanted to share the excellent feedback on the piling works for Barrier Gardens Pier. A success all round project in terms of task at hand, depth, timing, budget, comms and health and safety.  We’d be happy to work with the Red7Marine team again and I shall be in touch as soon as something comes up. Please pass on our thanks to the team for making the project a success.”

Richard Hopperton, Head of Procurement Port of London Authority