Loughor Site Investigation

Case Study Overview

Red7Marine (R7M) supplied the 18x18m modular jack up platform, Haven Seajack 1, to provide a stable working platform to conduct site investigations works from at the Loughor Viaduct in South Wales. The barge was manoeuvred on site by R7M’s road transportable workboat the Taska 1. The site investigation works are to be utilised in the design of a replacement rail bridge at the location in 2012.

At a glance

  • Location: South Wales
  • Date: June to July 2011
  • Programme Duration: 2 months
  • Project Number: 2406
  • Value: £150,000
  • Client: Network Rail
  • Principal Contractor: ESG (Soil Mechanics)

The Solution

This location provided a series of challenges including restrictive air draught, close proximity to structures, strong currents, large tidal range and very varied soil strata.

Having been approached by our client, R7M performed a site visit where these restrictive factors were identified, the most pressing of which was the requirement to pass under low power cables. After surveying the cables the maximum allowable leg length that could safely transit the cables were identified.

This however then restricted the leg available to perform the required tasks on site. Therefore R7M identified suitable tidal windows to accommodate for the varied soil strata, which provided estimated penetrations of over 7m, and still utilise the restrictive leg length to ensure that the barge remained operating safely.

In addition to the air draught and penetration restrictions, the area also exhibited strong tidal flows and large tides, due to its close proximity to the River Severn. This meant that relocation of the barge was a time critical operation and R7M’s Taska 1 workboat proved to be the perfect vessel. Due to draught restrictions on the approach to site and its general location it meant that there were limited vessels available to assist in relocating the barge from borehole to borehole. The Taska 1 had a shallow enough draught to work in the area and was able to strap onto the barge to accurately relocate it within 1.5m of the existing structure.

The soils information obtained from this site investigation, which was only possible through the use of a jack up platform, will now be utilised in the design of the foundations for the replacement rail bridge.

Loughor Site

Loughor Site

THE MARINE PARTNER OF CHOICE

SEE RELATED CASE STUDIES

Brighton

Brighton Marina
Phase 2

In order to accommodate a new luxury apartment block in Brighton, part of the marina needed to be reclaimed using sheet piled cofferdams. This would enable the water to be kept out and foundations to be built for the stunning seafront properties. Red7Marine supported the installation of a sheet pile twin wall cofferdam.

Read more →

Oldbury

Oldbury

Red7Marine installed replacement Active Effluent Discharge Lines at Oldbury power station as part of the on-going care and maintenance works. Red7Marine’s previous project experience on similar projects consisting of works on subsea pipeline and outfalls at Bradwell and Sizewell nuclear power stations, positioned the company as the ideal marine partner for client, Magnox.

Read more →

Emirates

Emirates Cable Car

The Emirates cable car was installed to provide a pedestrian link across the River Thames between the Royal Docks and the Greenwich peninsula. Red7Marine worked with Bachy Soletanche in a joint venture to install the foundations for the one-kilometre long cable car using marine rotary bored piling.

Read more →

Battersea

Battersea River Pier

Red7Marine secured a contract at Battersea in December 2016 to install new tubular driven steel mooring piles for the Battersea Power Station river bus pontoon installation which is planned to be operational in Autumn 2017. Transport for London (TFL) decided to extend the river bus service after the number of housing developments at Battersea began to increase.

Read more →

Middleton

Middleton Sands Navigation Marker

This fast turn-around marine construction project involved the installation of a new tubular steel navigation marker pile at Middleton Sands, Barrow-in-Furness in 2017. The navigation marker was required to identify the sub surface obstructions and enable other vessels in the area to operate safely.

Read more →

Liverpool 2

Liverpool 2 Deep Water Port Extension

Red7Marine was the marine partner of choice for BAM Nuttall when they constructed a piled combi-wall as part of the Liverpool 2 Dock Expansion that began in 2014. The construction of the container terminal was supported by four of Red7Marine’s jack up barges; the Haven Seariser 1, Haven Seariser 2 and the Haven Seariser 3 and the Haven Seajack as it carried out rock socket piling works.

Read more →

Weston Super Mare

Weston-Super-Mare

The Red7Marine team was chosen to provide specialist marine plant and personnel to aid the redevelopment of the Weston-super-Mare Grand Pier after it was destroyed in a fire in 2008. Red7Marine supplied the Haven Seajack 4 assisted in the pier construction works. Its previous experience in pier and marina construction works made it the ideal project partner for this development.

Read more →

Bradwell

Bradwell Power Station Barrier Wall Removal

Red7Marine is a leading provider of equipment for marine demolition and is skilled in dismantling structures that are beyond the reach of ordinary demolition contractors. In 2012, Red7Marine removed approximately 800 tonnes of steel in the Blackwater Estuary from the Bradwell nuclear power station water intake structure.

Read more →

Fingringhoe

Fingringhoe Firing Ranges

Red7Marine installed scour protection and provided remediation on damaged sections of the flood defences to preserve areas of the salt marsh at the Fingringhoe firing ranges in Essex. Scour protection and remediation techniques are used to control erosion in both estuarine and the offshore environments.

Read more →

Get in touch with our expert team

or speak to our team: 01255 886710

British Standards ISO British Standards ISO British Standards ISO Achilles Building Confidence IEMA Construction Line Chas Ijuboa CPA National Workboat Association ICE Mates in Mind AF Covenenant Gold award

“It is always a pleasure working with such a highly motivated and professional team, from office to site team working alongside us we could not ask for any better working partnership between our companies. Once again, many thanks and look forward to our next project.”

Lawrence Rogers, Works Manager Mackley