Great Yarmouth Outer Harbour

Case Study Overview

Diving contractor responsible for all health & safety planning and team/equipment support to perform visual and tactile bed-level survey to locate obstructions to piling operations.

Full surface supply diving equipment, Broco cutting equipment and team operating off client supplied floating plant. The dive team located debris using circular search patterns& installed lifting points to steel sheet pile debris using Broco ultra-thermic cutting equipment. Rigging was subsequently installed for lifting operations using client lifting plant.

At a glance

  • Location: Great Yarmouth Outer Harbour – North and South breakwater arms
  • Project Value: Award £5,500, Outturn £5,500 (NB support costs only)
  • Programme Duration: 3 days including mob/demob – all work completed in 3 days.
  • In-House resources Work: Supply of all diving H&S documentation for diving support works, as well as supply of containerised surface supply diving equipment, Broco cutting equipment and team
  • Contract: Van Oord Purchase Order agreement

The Solution

Initial enquiry was taken on a Sunday afternoon and mobilisation of team and equipment undertaken early the next day. All scheduled support work was executed in a safe manner and delivered on time and within agreed budget.

Agreed diving support scope was successfully achieved, however the lifting capacity of the client supplied lifting plant was not sufficient to remove the piles from their embedded location. Excavation options were put to the client, however the decision was taken to move the caisson centreline by 0.5m thus out of alignment with the debris – R7M subsequently provided diving support to ensure that this was achieved thus ensuring there were no further obstructions to piling operations.

Value Added
Provision of suitable methodology to achieve the works, containerised dive system, underwater cutting equipment & suitable tested rigging to undertake the operations.

Lift of caisson into positionGreat Yarmouth

Caisson installed
Great Yarmouth

THE MARINE PARTNER OF CHOICE

SEE RELATED CASE STUDIES

Brighton

Brighton Marina
Phase 2

In order to accommodate a new luxury apartment block in Brighton, part of the marina needed to be reclaimed using sheet piled cofferdams. This would enable the water to be kept out and foundations to be built for the stunning seafront properties. Red7Marine supported the installation of a sheet pile twin wall cofferdam.

Read more →

Oldbury

Oldbury

Red7Marine installed replacement Active Effluent Discharge Lines at Oldbury power station as part of the on-going care and maintenance works. Red7Marine’s previous project experience on similar projects consisting of works on subsea pipeline and outfalls at Bradwell and Sizewell nuclear power stations, positioned the company as the ideal marine partner for client, Magnox.

Read more →

Emirates

Emirates Cable Car

The Emirates cable car was installed to provide a pedestrian link across the River Thames between the Royal Docks and the Greenwich peninsula. Red7Marine worked with Bachy Soletanche in a joint venture to install the foundations for the one-kilometre long cable car using marine rotary bored piling.

Read more →

Battersea

Battersea River Pier

Red7Marine secured a contract at Battersea in December 2016 to install new tubular driven steel mooring piles for the Battersea Power Station river bus pontoon installation which is planned to be operational in Autumn 2017. Transport for London (TFL) decided to extend the river bus service after the number of housing developments at Battersea began to increase.

Read more →

Middleton

Middleton Sands Navigation Marker

This fast turn-around marine construction project involved the installation of a new tubular steel navigation marker pile at Middleton Sands, Barrow-in-Furness in 2017. The navigation marker was required to identify the sub surface obstructions and enable other vessels in the area to operate safely.

Read more →

Liverpool 2

Liverpool 2 Deep Water Port Extension

Red7Marine was the marine partner of choice for BAM Nuttall when they constructed a piled combi-wall as part of the Liverpool 2 Dock Expansion that began in 2014. The construction of the container terminal was supported by four of Red7Marine’s jack up barges; the Haven Seariser 1, Haven Seariser 2 and the Haven Seariser 3 and the Haven Seajack as it carried out rock socket piling works.

Read more →

Weston Super Mare

Weston-Super-Mare

The Red7Marine team was chosen to provide specialist marine plant and personnel to aid the redevelopment of the Weston-super-Mare Grand Pier after it was destroyed in a fire in 2008. Red7Marine supplied the Haven Seajack 4 assisted in the pier construction works. Its previous experience in pier and marina construction works made it the ideal project partner for this development.

Read more →

Bradwell

Bradwell Power Station Barrier Wall Removal

Red7Marine is a leading provider of equipment for marine demolition and is skilled in dismantling structures that are beyond the reach of ordinary demolition contractors. In 2012, Red7Marine removed approximately 800 tonnes of steel in the Blackwater Estuary from the Bradwell nuclear power station water intake structure.

Read more →

Fingringhoe

Fingringhoe Firing Ranges

Red7Marine installed scour protection and provided remediation on damaged sections of the flood defences to preserve areas of the salt marsh at the Fingringhoe firing ranges in Essex. Scour protection and remediation techniques are used to control erosion in both estuarine and the offshore environments.

Read more →

Get in touch with our expert team

or speak to our team: 01255 886710

British Standards ISO British Standards ISO British Standards ISO Achilles Building Confidence IEMA Construction Line Chas Ijuboa CPA National Workboat Association ICE Mates in Mind AF Covenenant Gold award

“I wanted to share the excellent feedback on the piling works for Barrier Gardens Pier. A success all round project in terms of task at hand, depth, timing, budget, comms and health and safety.  We’d be happy to work with the Red7Marine team again and I shall be in touch as soon as something comes up. Please pass on our thanks to the team for making the project a success.”

Richard Hopperton, Head of Procurement Port of London Authority